Abstract
Objective Large-diameter lifesaving holes have been successfully applied multiple times in mine rescue through surface drilling. However, they show limitations in emergency response like quick dispatch and cross-regional rescue, and their technological adaptability is insufficient to cope with complex strata. Methods From the perspective of overall emergency rescue, with rescue timeliness as an indicator, this study summarized the critical technologies like response capability enhancement and borehole-forming technology for complex strata. It constructed an emergency handling process for mine rescue through surface drilling, specified the improvements in contingency plan activation, response actions, and response speeds, and established the hierarchical cross-regional rescue dispatch mechanism and the pre-drilling technical support response mechanism. Based on the analysis of the drilling process characteristics of large-diameter lifesaving holes in unconsolidated strata and bedrock layers, this study proposed solutions to construction challenges in complex strata characterized by fragmentation and high water inflow, and typical problems in the rescue lifting process. Results and Conclusions Key findings are as follows: (1) A scientific emergency response mechanism for mine rescue through surface drilling is a significant approach for improving rescue efficiency. The emergency response efficiency can be effectively increased by 2.3 times by employing the hierarchical cross-regional rescue dispatch mechanism and the pre-drilling technical support response mechanism. (2) An efficient borehole-forming solution for large-diameter lifesaving holes under complex formation conditions is developed in this study. The solution is applied to the experimental project of the Jiudingshan mine in Jining City, completing a large-diameter lifesaving hole with a final drilling depth of 403.2 m, a diameter of 580 mm at the end location, and an average penetration rate of 2.5 m/h. The total duration from emergency response to rescue lifting takes 311.95 h, improving the overall rescue timeliness by 47%. (3) In terms of rescue timeliness, the efficiency improvement of the rescue preparation phase is superior to that of the implementation phase, with more achievable enhancement in the emergency response capability. Therefore, mine rescue teams are recommended to enhance emergency preparedness and rapid response capabilities in the case of limited enhancement in drilling technology and equipment. The results of this study can be referenced for supplying surface emergency rescue for mines with mining depths shallower than 400 m, guiding mine rescue teams to establish emergency response mechanisms, and conducting construction design for large-diameter lifesaving holes, thus holding significant guiding implications for mine emergency rescue through surface drilling.
Keywords
mine rescue through surface drilling, emergency rescue mode, emergency response, large-diameter lifesaving hole, borehole-forming technology
DOI
10.12363/issn.1001-1986.24.06.0385
Recommended Citation
MA Tan, ZHUGE Lei, ZHAO Weidong,
et al.
(2024)
"Emergency response and critical technologies for large-diameter boreholes in mine rescue through surface drilling,"
Coal Geology & Exploration: Vol. 52:
Iss.
9, Article 19.
DOI: 10.12363/issn.1001-1986.24.06.0385
Available at:
https://cge.researchcommons.org/journal/vol52/iss9/19
Reference
[1] 袁亮,张平松. 煤炭精准开采地质保障技术的发展现状及展望[J]. 煤炭学报,2019,44(8):2277−2284.
YUAN Liang,ZHANG Pingsong. Development status and prospect of geological guarantee technology for precise coal mining[J]. Journal of China Coal Society,2019,44(8):2277−2284.
[2] 陈卫明,王家文,凡东,等. 矿山救援钻孔中井涌井漏事故预警预测[J]. 煤田地质与勘探,2024,52(3):144−152.
CHEN Weiming,WANG Jiawen,FAN Dong,et al. Early warning and prediction of kicks and lost circulation accident during rescue drilling of mine[J]. Coal Geology & Exploration,2024,52(3):144−152.
[3] 张彪,康玉国,黄勇,等. 矿山救援地面生命保障孔高效成孔关键技术[J]. 煤田地质与勘探,2022,50(11):14−23.
ZHANG Biao,KANG Yuguo,HUANG Yong,et al. Key technologies of surface efficient life support hole forming for mine rescue[J]. Coal Geology & Exploration,2022,50(11):14−23.
[4] 黄军利. 国外煤矿应急救援技术装备综述[J]. 煤矿安全,2016,47(9):233−236.
HUANG Junli. A review of foreign technical equipment on coal mine emergency rescue[J]. Safety in Coal Mines,2016,47(9):233−236.
[5] 董泽训. 山东笏山矿难3号救援钻孔施工技术[J]. 钻探工程,2021(10):104−109.
DONG Zexun. Construction technology of No. 3 rescue borehole in Hushan Mine disaster,Shandong province[J]. Drilling Engineering,2021(10):104−109.
[6] 凡东,邹祖杰,王瑞泽,等. 地面救援车载钻机的研制[J]. 煤田地质与勘探,2022,50(11):35−44.
FAN Dong,ZOU Zujie,WANG Ruize,et al. Development of rescue truck-mounted drilling rig in ground emergency[J]. Coal Geology & Exploration,2022,50(11):35−44.
[7] 常江华. 全液压车载钻机回转系统设计[J]. 煤矿安全,2018,49(2):115−117.
CHANG Jianghua. Design of rotary system for all hydraulic truck-mounted drilling rig[J]. Safety in Coal Mines,2018,49(2):115−117.
[8] 徐俏武,张小新. 液压动力猫道钻杆减阻控制优化研究[J]. 制造业自动化,2021,43(11):144−147.
XU Qiaowu,ZHANG Xiaoxin. Optimization of hydraulic power catwalk drill pipe drag reduction control system[J]. Manufacturing Automation,2021,43(11):144−147.
[9] 甘心,殷琨,何将福,等. 救援井用大直径贯通式潜孔锤及钻头的研制[J]. 吉林大学学报(工学版),2015,45(6):1844−1851.
GAN Xin,YIN Kun,HE Jiangfu,et al. Development and test of a large diameter hollow—Through DTH air hammer and drill bit used in rescue well[J]. Journal of Jilin University (Engineering and Technology Edition),2015,45(6):1844−1851.
[10] 王立峰,张晓昂,徐影. 单体大直径空气潜孔锤钻井工艺研究及应用[J]. 中国煤炭地质,2021,33(8):65−67.
WANG Lifeng,ZHANG Xiaoang,XU Ying. Study on and application of unicum large diameter pneumatic DTH hammer drilling technology[J]. Coal Geology of China,2021,33(8):65−67.
[11] 田宏亮,邹祖杰,郝世俊,等. 矿山灾害生命保障救援通道快速安全构建关键技术与装备[J]. 煤田地质与勘探,2022,50(11):1−13.
TIAN Hongliang,ZOU Zujie,HAO Shijun,et al. Key technologies and equipment of quickly and safely building life support and rescue channel in mine disaster[J]. Coal Geology & Exploration,2022,50(11):1−13.
[12] 周兢. 矿山灾害应急救援生命保障孔钻井工艺研究[J]. 钻探工程,2022(1):128−134.
ZHOU Jing. Research on drilling technology for mine disaster rescue life support holes[J]. Drilling Engineering,2022(1):128−134.
[13] 武程亮,滕子军,赵后明,等. 矿山钻探应急救援中生命通道的钻井技术以山东栖霞笏山金矿事故救援 1 号孔为例[J]. 钻探工程,2021,48(增刊1):206−210.
WU Chengliang,TENG Zijun,ZHAO Houming,et al. Drilling technology for the lifeline channel in mine emergency rescue a case study of the accident rescue of the Hushan Gold Mine in Qixia city,Shandong province[J]. Drilling Engineering,2021,48(Sup.1):206−210.
[14] 山东省临沂市应急办. 山东平邑“12·25” 石膏矿坍塌事故救援工作纪实[J]. 中国应急管理,2016(1):47−48.
Linyi Emergency Management Bureau. On-the-spot report on rescue work of “12.25” gypsum mine collapse accident in Pingyi,Shandong Province[J]. China Emergency Management,2016(1):47−48.
[15] 渠伟,李新年,张堃,等. 大口径救援生命通道的施工工艺及钻具配置[J]. 中国安全生产科学技术,2016,12(增刊1):44–48.
QU Wei,LI Xinnian,ZHANG Kun,et al. Construction technology and drilling tools configuration of large diameter life rescue channel[J]. Journal of Safety Science and Technology,2016,12(Sup.1):44–48.
[16] 唐永志,赵俊峰,丁同福,等. 复杂地质条件下大直径救生孔成孔关键技术与工艺[J]. 煤炭科学技术,2018,46(4):22−26.
TANG Yongzhi,ZHAO Junfeng,DING Tongfu,et al. Key technology and technique of large diameter rescue borehole drilling under complicated conditions geological[J]. Coal Science and Technology,2018,46(4):22−26.
[17] 郝世俊,莫海涛. 地面大直径应急救援钻孔成孔工艺设计与分析[J]. 煤田地质与勘探,2021,49(1):277−284.
HAO Shijun,MO Haitao. Design and analysis of hole-forming technology for surface large diameter emergency rescue borehole[J]. Coal Geology & Exploration,2021,49(1):277−284.
[18] 赵江鹏,刘建林,赵建国. 矿山大口径钻孔循环钻进技术研究[J]. 金属矿山,2018(1):147−151.
ZHAO Jiangpeng,LIU Jianlin,ZHAO Jianguo. Research on reverse circulation drilling technology for large-diameter mine drilling hole[J]. Metal Mine,2018(1):147−151.
[19] 程林,李艳丽,尹建国,等. 平邑石膏矿坍塌事故5号救生孔施工工艺及钻具配置[J]. 探矿工程(岩土钻掘工程),2016,43(5):13−16.
CHENG Lin,LI Yanli,YIN Jianguo,et al. Construction technology of 5# rescue hole in the collapse accident in Pingyi gypsum mine and the drilling tool configuration[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling),2016,43(5):13−16.
[20] 杨三军,朱新菲,谭波. 基于云模型的矿山应急救援队伍能力评估标准研究[J]. 煤矿安全,2021,52(11):250−255.
YANG Sanjun,ZHU Xinfei,TAN Bo. Evaluation standard of mine emergency rescue force capability based on cloud model[J]. Safety in Coal Mines,2021,52(11):250−255.
[21] 邹逸江,孔家辉,斯港杰. 综合应急救援能力描述理论架构及提升内容研究[J]. 灾害学,2021,36(2):145−150.
ZOU Yijiang,KONG Jiahui,SI Gangjie. Research on theoretical framework and improvement content of capability description in comprehensive emergency rescue[J]. Journal of Catastrophology,2021,36(2):145−150.
[22] 顾海荣,单增海,王龙鹏,等. 大直径钻孔救援提升装备研究进展[J]. 煤田地质与勘探,2022,50(11):45−57.
GU Hairong,SHAN Zenghai,WANG Longpeng,et al. Research progress of lifting equipment for large-diameter borehole rescue[J]. Coal Geology & Exploration,2022,50(11):45−57.
[23] 莫海涛,郝世俊,叶根飞. 煤矿区大口径井二开先导孔下导管钻进技术[J]. 煤田地质与勘探,2014,42(4):106−108.
MO Haitao,HAO Shijun,YE Genfei. Drilling technology with guide pipe in the second section pilot hole of large-diameter well in coal mining area[J]. Coal Geology & Exploration,2014,42(4):106−108.
[24] 莫海涛. 集束式潜孔锤水柱密封反循环形成机理与过程控制研究[D]. 北京:煤炭科学研究总院,2021.
MO Haitao. Research on reverse circulation formation mechanism and process control of cluster-type pneumatic DTH hammer with water column seal downhole[D]. Beijing:China Coal Science Research Institute,2021.
[25] 王程林,王明耀,王翠. 矿山大口径钻孔钻探施工技术及工艺研究[J]. 中国煤炭地质,2022,34(增刊2):26−28.
WANG Chenglin,WANG Mingyao,WANG Cui. Research on construction technology of large diameter drilling in mines[J]. Coal Geology of China,2022,34(Sup.2):26−28.
[26] 刘凯都,刘书杰,文敏. 物理化学作用下定向井井壁稳定分析[J]. 复杂油气藏,2019,12(3):64−67.
LIU Kaidu,LIU Shujie,WEN Min. Stability analysis of directional wellbore wall under physicochemical action[J]. Complex Hydrocarbon Reservoirs,2019,12(3):64−67.
Included in
Earth Sciences Commons, Mining Engineering Commons, Oil, Gas, and Energy Commons, Sustainability Commons